Scope of the Project:
The
objective of the project was to add 6 new large classrooms to the existing school
to accommodate increased student enrolment. The intent for this phase was to design
the new building to accommodate the future addition of a second floor of classrooms
and make allowance for the potential to expand the existing gymnasium or add a new
gymnasium.
|
Classrooms
|
6
|
|
Washrooms
|
2
|
|
Site preparation for Phase
II & III
|
|
|
Number of Stories
|
1
|
|
Area of Construction
|
563 sq m / 6,000 sq ft
|
|
Number of students utilizing
the new building
|
150
|
|
Completion date
|
Sept. 2007
|
|
Total Cost
|
$1, 200,000
|
The
project was completed, as described in the drawings: six new classrooms on one floor
with concrete masonry exterior walls and wood stud/ drywall partition walls. The
floor is concrete slab on grade and the roof (future second floor) is constructed
with precast concrete panels. Designated boys and girls washrooms and a mechanical
room were completed. The building is fully sprinklered and the necessary heating
and ventilating was provided. Civil work included a new sanitary, storm and water
connection to the new building. Site work included the expansion of the paved parking
area, an open courtyard between the old and new buildings and miscellaneous landscape
work.